|
|
|
C
O N S E R V A T O R Y B L O G
A
u g u s t 2 0 0 5
|
| |
| Monday
29th August 2005 |
|
Guttering,
Trim and Tiles
|
| |
Since the last update I've
been busy fixing the doors into their final position, adding all the trim
and sealant, but mosty
importantly, getting the guttering in place.
On Saturday my dad came over
(again!) and we got started getting the floor tiles down. We needed to
use a levelling compound to bring the floor level. We also needed to use
a PVA based solution to seal the porous concrete base. This took most
of Saturday - together with the guttering.
Once that was done, we could
measure up for the tiles and get them all down. This took all of Sunday.
Bank holiday was spent grouting
and cleaning the tiles.
|
| |
|
| |
Today's pearl
of wisdom:
Buy a proper tile cutter (around £15 from B&Q),
it will save you no end of broken tiles!
|
| |
| |
 |
|
|
|
Guttering
and Trim in place
|
|
Tiled
floor finished
|
|
| |
| Wednesday
23rd August 2005 |
|
Storms-a-brewing! (stage
9)
|
| |
As you can see from the photo
below, the tarpaulin collected a substantial amount of rain water during
Monday. When I got in from work, I found the tarpaulin wrenched from it's
fixings by the weight of the water and on the brink of depositing said
water into the conservatory.
With rain and gales forecast
for Wednesday and Thursday we decided that the tarpaulin would not be
up to the job and that we needed to get the real roof on before the bad
weather arrived.
At 19:00 on Monday, we set
about fixing the roof in place. There is almost no physical space between
the neighbours fence and the side of the conservatory, so all trimming
and decorative fixings needed to be attached as we went, through the gap
in the roof. This was reasonable easy, but required time and thought to
make sure we did everything in the correct order and didn't miss anything.
Because of this, we only managed
to get the first of the 3 polycarbonate roof sheets in place on Monday
evening before it got dark. I took an emergency morning off work on Tuesday
morning to get the remaining 2 roof sheets into place.
In the evening, I hung the
doors, though these have yet to be properly aligned.
|
| |
| |
 |
|
|
| Rain water
gathering |
|
All
right on the night
|
| |
|
|
 |
|
|
| Just the
trim and guttering to go |
|
Enjoying
the space
|
|
| |
| Sunday
21st August 2005 |
|
Cheese
Infill (stage 9)
|
| |
My dad popped over again today
and we started getting the roof 'cheese infills' into place. This are
triangular 'cheese' shaped pieces which help give the roof it's slope.
We discovered that the conservatory
is approx 1cm narrower at the back than at the front. We're not sure how,
but hopefully this isn't going to be a problem.
The single most important piece
of the conservatory is the rear roof beam, which bears most of the roof
weight. This had to be attached to the wooden frame we constructed in
stage
8. It has always
been marginal as to whether this beam would fit in under the existing
house roof guttering, or whether the guttering would need to be moved
somehow in order to accommodate the beam. I'm very pleased to say that
our original calculations (going back to April, before we ordered the
conservatory) were almost spot on and although there's not a lot of clearance,
the beam does fit just under the guttering. This is a major bonus as we
now can leave the house guttering in place.
Oh, and we also ran out of
silicone sealant!
|
| |
| Saturday
20th August 2005 |
|
Framed (stage
9)
|
| |
We've been working all week
on getting the window panels into place and I fixed the last panel into
position Thursday (though the last panel will have to come out again in
order to fix the doors). They all went in without a hitch which is a good
sign that we got our measurements correct in the early days!
Ros popped down to Travis Perkins
and got hold of a cavity closer. This is a small plastic thing filled
with expanded polystyrene which sits in the wall cavity, between the base
and outer wall that would otherwise be under your foot as you step out
of the door.
Getting the door frame in was
quite a substantial job as it required a lot of measuring and testing
before we could actually fit it. I had to add a small slither of packing
to vertically even the wooden frame up with the dwarf wall on which is
sits. A small amount of packing was also required under the door frame
to bring it to the correct height.
Once this was in all in place,
we had to take the last window panel back out, fit the door frame - bolting
it into the dwarf wall, then re-fit the last window panel. This is because
you must finish the panel fitting with a corner panel, in order to get
all the correct screws and bolts in. It was all extremely 'snug' (tight!),
but we managed it in the end.
|
| |
| |
 |
|
|
|
In
the frame
|
|
Ready
for the roof
|
|
| |
| Tuesday
16th August 2005 |
|
Windows! (stage
9)
|
| |
Ros and I started work tonight
on putting up the window units and we've now got the first two panels
in place.
It's tricky work though because
of the limited access we have to the left hand side of the conservatory
(because of the fence). We're basically having to ensure that we're creating
water tight seals and adding all trimming and decorative bits, as we add
each panel. Once the whole conservatory is finished, it will be impossible
to physically get down the side of the conservatory, so we have to make
a good job of it first time!
We're hoping that the lack
of access down one side of the conservatory won't be a problem for putting
the roof on, but it's something of an unknown at the moment.
|
| |
| |
 |
|
|
|
First
two Window panels in place
|
|
Difficult
to see... but they are there!
|
|
| |
| Sunday
14th August 2005 |
|
Onwards
and Sideways... (stage 9)
|
| |
During the last week I've been
working on and off fitting the timber frame, which I've now finished.
This included cladding the frame on the outside with waterproof PVC slats.
When the conservatory is up, the timber frames will be filled with insulation
and covered with plasterboard, which eventually will be plastered over.
My dad came down yesterday
and we started work on actually putting up the conservatory! stage
9.
We've only got the sills done so far, but we hope the rest will go up
quite quickly. The instructions that come with the conservatory leave
a lot to be desired though!
|
| |
| |
 |
|
|
| Frame
clad in UPVC. Pitty about the Weather! |
|
Keeping
the rain off!
|
| |
|
|
 |
|
|
| Starting
work on the Conservatory |
|
Sills
in place
|
|
| |
| Tuesday
2nd August 2005 |
|
Timber! (stage
8)
|
| |
Another productive weekend
saw the half of the timber frame constructed for stage
8 of the conservatory.
The timber frame sits under the roof soffit and fills the gap between
the conservatory and the house. It's vital that the timber frame is structurally
sound as it will have to provide the support for the conservatory walls
and roof. For this reason the frame is made from thick 3" x 4" timber.
It's then bolted to the wall
using special metal anchor bolts, bolted to the dwarf wall using more
anchor bolts and screwed to the roof timbers (exposed by removing the
soffit board). Basically, it's not going anywhere!
The finished frame will be
cladded on the outside with white PVC slats to protect from the elements,
filled with insulation and have plaster board on the inside. But that's
next weekends job.
|
| |
| |
 |
|
|
|
Wooden
Frame, bolted to the walls...
|
|
...
and screwed to the roof timbers
|
|
| |
|